PIB Clearance for the Project
|
17.04.1980
|
|
|
Land acquisition
|
07.07.1980
|
|
|
Project
Zero Date |
31.03.1981
|
|
|
Foundation Stone laying by Late Prime Minister Smt.
Indira Gandhi
|
05.02.1982 |
|
|
Mech. completion of Plants :
a. 1st Phase of Ammonia & two streams of Urea plants
b. 2nd Phase of Ammonia & two streams of Urea plants
|
30.04.1984
31.08.1984
|
|
|
Receipt of gas for - Phase-1
Phase-2
|
18.09.1985
06.11.1985
|
|
|
Commencement of Trial production - Ammoni
Urea
|
14.11.1985
26.11.1985
|
|
|
Start of Commercial Production - Ammonia & Urea
|
01.03.1986
|
|
|
|
|
|